Construction has begun on this year’s Street Improvement Project. The contractor has split the project into four areas for coordination and scheduling.
- Area 1: 46th Street N, 47th Street N, 48th Street N and 49th Street N (From Hadley Avenue N to the East) Area 1 Map
- Area 2: Hadley Avenue N from 40th Street N to 50th Street N Area 2 Map
- Area 3: Oakdale Nature Preserve Trail Reconstruction Area 3 Map
- Area 4: North Fire Station Parking Lot Reconstruction Area 4 Map
Improvements on Hadley Avenue N include miscellaneous storm sewer repairs, spot curb and gutter replacement, full asphalt replacement, street light replacement and bike trail reconstruction on the west side of Hadley Avenue N.
The improvements in the residential areas east of Hadley Avenue N include miscellaneous storm, sanitary and water main repairs, spot curb and gutter replacement, street light replacement and full asphalt pavement replacement.
Dresel Contracting is the contractor for this project. They have successfully completed many similar local projects. All project work is scheduled to be completed by the end of September.
Current and Planned Work
Area 1: 46th Street N, 47th Street N, 48th Street N and 49th Street N (From Hadley Avenue N to the East)
- Please help water your sod so it grows! The contractor will also water for the first 30 days only. Any sod that is acceptable after 30 days will not be replaced. See the sod care sheet for more information.
Area 2: Hadley Avenue N (40th Street N to 50th Street N)
- Please help water your sod so it grows! The contractor will also water for the first 30 days only. Any sod that is acceptable after 30 days will not be replaced. See the sod care sheet for more information.
Area 3: Oakdale Nature Preserve Trail Reconstruction
- Grading has started and will be completed on Friday, August 23.
- Trail paving started today, Thursday, August 22 and will be completed Saturday, August 24.
- Concrete curb and pedestrian ramps are tentatively scheduled for the end of next week.
- Topsoil and seeding is planned for next week.
Area 4: North Fire Station Parking Lot Reconstruction
- The final layer of asphalt is scheduled for early next week.
Reminders
As construction progresses, please use caution traveling within the project area. Also, please do not park vehicles on the street from 7 AM to 7 PM within the project area unless instructed to by the contractor to accommodate driveway work. This will help the contractor to work more efficiently and will create a safer work zone. Thank you, as always, for your ongoing patience and cooperation.
If you have any questions regarding this project, please feel free to call:
- Mike LaDoux, E.I.T, Project Representative with SEH 651-256-0438
- Brian Bachmeier, P.E., Consulting City Engineer 651-730-2730