2020 Street Improvement Updates

August 19, 2021

Construction continues on this year’s street improvement project. The contractor has split the project into smaller areas for coordination and scheduling:
  1. Area 1: The Shenandoah neighborhood located east of I-694 and north of 50th Street. View area 1 map.
  2. Area 2: The commercial industrial areas east and west of I-694, north of 4th Street and south of 10th Street. View area 2 map.
  3. Area 3: The Oakdale Park trail from Hadley Avenue to the Discovery Center and west to Granada Avenue. View area 3 map.
The improvements include miscellaneous storm sewer/sanitary sewer/water main repairs and replacement, replacement of isolated sections of structurally damaged curb and gutter, repaving of the asphalt pavement section, installation of new street lighting, and some trail and walk improvements.

MN Paving is the contractor for this project. They have successfully completed many similar projects for the City. All project work is scheduled to be complete by early September.

Current and Planned Work

Please read the sod care instructions, water your sod, and do not mow it now!


Area 1

Shenandoah Valley neighborhood located east of I-694 and north of 50th Street

  • All work is now complete except for clean-up items and a backyard storm sewer outlet cleaning next to I-694 which will be done after a permit is received. 

Area 2 

Commercial-industrial area east of I-694, north of 4th Street and south of 10th Street

East of I-694
  • Boulevard areas have been restored with sod except for Helena Avenue which will be done in a couple of weeks after the sidewalk is completed. A couple small areas were delayed by underground telecommunications relocations.
  • The Powerline Park trail realignment is now paved.  Topsoil and seeding along the edges is planned for the week of August 30.
  • Street lights are planned to be installed the first two weeks of September. There has been a delay due to supply chain challenges.
  • The final layer of asphalt will be paved in mid-September after the lights are installed.
West of I-694
  • Boulevard topsoil and sod placement is planned for the next week. 
  • Street lights are planned to be installed the first two weeks of September. There has been a delay due to supply chain challenges.
  • The final layer of asphalt will be paved in mid-September after the lights are installed.

Area 3

Oakdale Park trail from Hadley Avenue to the Discovery Center and west to Granada Avenue

  • The trail is now closed until complete. Please use alternate trails to allow the contractor to get the required work done as efficiently and safely as possible.
  • The trail has been reclaimed into gravel and is now being graded and prepared for paving.
  • Trail paving is scheduled for next Thursday and Friday (August 26 & 27).
  • Restoration of the edges of the trail will follow the completion of the pavement and is scheduled to be the week of September 6.
As construction progresses, please use caution traveling within the project area. Also, please do not park vehicles on the street from 7 am to 7 pm within the project area unless instructed to by the contractor to accommodate driveway work. This will help the contractor to work more efficiently, and will create a safer work zone. Thank you, as always, for your ongoing patience and cooperation.

If there are any questions or comments regarding the project, please contact one of the following people:
  • Joe Meemken, 651-724-5588, On Site Project Representative, SEH
  • Brian Bachmeier, 651-730-2730, Oakdale Public Works Director/City Engineer
  • Todd Blank, 651-490-2017, Project Manager, SEH
Share on Facebook
Share on Twitter
Share via Email

Copyright 2021. City of Oakdale. All Rights Reserved.
1584 Hadley Avenue N., Oakdale, MN 55128

Powered by
CivicSend - A product of CivicPlus